Insignia

AIP & AoN

HQ Eastern Command

Approval In Principle & Acceptance of Necessity

Total Estimated Cost

₹ 75 L

Project Duration

18 Months

Plinth Area

150 Sq.M

Current Status

Awaiting Approval

Project Information

1. Acceptance of Necessity (AoN)

2. Approval in Principle (AIP)

  • Rough Indication Cost (RIC) Report, Ref No. 100/A/75/E8(Wks)/25
  • Statement of Case (SoC) Report, Ref No. 100/A/75/E8(Wks)/25

Financials

Estimated Cost (RIC) ₹ 7,500,640.50
Cost in Words Rupees Seventy Five Lakh Six Hundred and Forty and Fifty Paise Only

3. Recommendations